Israel-1
Definition
Israel-1 is an AI supercomputer that NVIDIA built in Israel and fully funded itself, with no government investment. When it was announced in 2023, it was described as a testbed for the company's Spectrum-X networking platform. It is not part of Israel's national supercomputer program.
The 2023 announcement: a supercomputer-scale testbed
NVIDIA announced Israel-1 on May 29, 2023, at the Computex conference in Taipei, describing it as the most powerful supercomputer in Israel and one of the most powerful in the world. The plan presented at the time was a system reaching, at its peak, 8 exaflops of AI performance and more than 130 petaflops of traditional scientific computing, at an estimated value of several hundred million dollars, with 2,048 H100 GPUs and 2,560 BlueField-3 networking chips. The stated purpose was a testbed for NVIDIA's Spectrum-X networking platform, a basis for collaboration with partners, and support for the company's own internal research and development, alongside extending its DGX Cloud computing service to the regional ecosystem. Gilad Shainer, NVIDIA's senior vice president for HPC and networking, said: "Israel-1 represents a major investment that will help us drive innovation in Israel and globally." According to the plan, the system was to be running in NVIDIA's own facility by the end of 2023.
November 2023: phase one goes live, ahead of schedule
In practice the system started operating earlier than planned. According to SDxCentral, NVIDIA completed phase one of the project in under 20 weeks and opened access to its own research and development teams and to "select partners." Phase one included 128 HGX H100 systems, half of the full target scale, delivering 4 exaflops for AI and 65 petaflops for scientific computing. Phase two, planned for the first half of 2024, was meant to complete the system to 256 HGX H100 systems (2,048 H100 GPUs), 2,560 BlueField-3 chips and 80 Spectrum-4 switches, the full scale announced in 2023. Jensen Huang, NVIDIA's CEO, said at the opening: "Israel is home to world-leading AI researchers and developers creating applications for the next wave of AI." It was not explicitly published whether phase two was actually completed as planned.
Without a shekel of government money, and separate from the national program
Unlike government AI infrastructure, Israel-1 was fully funded by NVIDIA itself: the 2023 reports state explicitly that the project has no state investment. This is in contrast to a separate government supercomputer program, estimated at about $78 million, announced by the previous government (the Bennett-Lapid government); according to Ynetnews, NVIDIA's announcement could delay that program even further. Israel-1 is separate from the national artificial intelligence program now run by the Israel Innovation Authority (see the separate entry): that is a government program with its own supercomputer, funding source and timetable, and no connection between it and Israel-1 has been reported.
The broader context: a separate NVIDIA investment in Israel, not another supercomputer
In December 2025 NVIDIA announced a separate and much larger investment in Israel: a new R&D campus in Kiryat Tivon, on about 90 dunams (about 22 acres) and up to 160,000 square meters of built space, to house up to 10,000 employees. The investment was described as "a multi-billion-shekel investment," without an exact sum being published. Construction is planned to begin in 2027, with first occupancy in 2031. Unlike Israel-1, this campus is not a supercomputer, and the reporting on it did not link it to Israel-1. It is a separate investment by NVIDIA in its presence in Israel, not another phase or a declared expansion of the project described in this entry.
A new supercomputer near Yokneam, and Huang on "the economic impact"
According to Calcalist (December 2025), Israel-1 operates in Yokneam, in a 30-megawatt facility that cost about $500 million to build. The same report said that NVIDIA plans to build, in the Mevo Carmel industrial zone near Yokneam, a new and more advanced supercomputer that will exceed Israel-1 in capability: a facility that will consume about 64 megawatts, include the company's Blackwell chips, and bring the total investment to about NIS 4.84 billion (about $1.5 billion). Construction is expected to be completed about a year and a half after the agreement is signed. On February 4, 2026, at a joint press conference with Dassault Systèmes at the 3DEXPERIENCE World conference in Houston, Jensen Huang said: "The economic effects of a supercomputer are very deep," and "I'm very happy we are building the system." According to the Jerusalem Post, the "Israel 1" he mentioned is a supercomputer the company is building in the north of Israel. It was not clarified whether he meant an expansion of the 2023 system or the new supercomputer at Mevo Carmel, and as of October 2026 it has not been reported that the new facility is already operating.
FAQ ❓
When was Israel-1 announced, and who built it?
On May 29, 2023, at the Computex conference in Taipei, NVIDIA announced the construction of Israel-1 in Israel, a system it described as the most powerful supercomputer in Israel and one of the most powerful in the world, at an estimated value of several hundred million dollars.
What is Israel-1's stated purpose?
To serve as a testbed for NVIDIA's Spectrum-X networking platform, a basis for collaboration with partners and for the company's internal research and development, and to extend its DGX Cloud computing service to the regional ecosystem.
Did the state invest in Israel-1?
No. According to 2023 reports, the project was funded entirely by NVIDIA, with no government investment, unlike a separate government supercomputer program (about $78 million) announced by the Bennett-Lapid government.
What is the difference between Israel-1 and Israel's national artificial intelligence program?
Israel-1 is a private NVIDIA project; the national program, led by the Israel Innovation Authority, is a separate government program with its own supercomputer, budget and timetable. No declared connection between the two has been reported.
What is Israel-1's current status, as of 2026?
Israel-1 has been operating in Yokneam since phase one in 2023. In December 2025 Calcalist reported that NVIDIA is planning a new, more powerful supercomputer at Mevo Carmel, near Yokneam (about $1.5 billion in total, with Blackwell chips). As of October 2026 it has not been reported that the new facility is already operating.
Found a mistake, or have a source we should add? Write to us